The purpose of this project is to develop the link between academia and industry. Moreover, students will have a better understanding about the professional working environment. The opportunity is very suitable to enhance the engineering skills of the students.The Workshop Building contains electric
Designing of HVAC system of New Workshop Building of KElectric Korangi Town Gas Turbine Power Station
The purpose of this project is to develop the link between academia and industry. Moreover, students will have a better understanding about the professional working environment. The opportunity is very suitable to enhance the engineering skills of the students.The Workshop Building contains electrical/instrumental spare parts and machineries for which temperature control is an essential requirement. As we are aware that harsh weather conditions are not favorable for the heat producing machineries and for the spare parts kept in the stores and the tool room. So, in this regard a detailed HVAC design for New Workshop Building shall be developed in compliance with authority regulation & international standards.
The project involves site surveying to collect relevant data/information for proceeding the project. There are several methods employed globally for cooling load estimations where we would be using ‘Cooling Load temperature difference (CLTD) method’ and ‘ASHRAE-endorsed transfer function method’ HAP analysis for performing cooling load calculations and its validation.The tasks to be done for the completion of the project, initially includes complete site surveying for relevant data collection then drawing an architectural plan for the workshop building employing any suitable software (both ground and first floor). Calculating the cooling load for the building vicinity employing HAP software, and validation of results using manual calculations. Then designing the ducting system for suitable Air conditioning using MCQUAY duct sizer as well as representing the duct in the floor plan. Afterwards, selecting a reasonable chiller unit and AHU according to the load requirements.
The Workshop Building contains electrical/instrumental spare parts and machineries for which temperature control is an essential requirement. As we are aware that harsh weather conditions are not favorable for the heat producing machineries and for the spare parts kept in the stores and the tool room. So, in this regard a detailed HVAC design for New Workshop Building shall be developed in compliance with authority regulation & international standards.
The project involves site surveying to collect relevant data/information for proceeding the project. There are several methods employed globally for cooling load estimations where we would be using ‘Cooling Load temperature difference (CLTD) method’ and ‘ASHRAE-endorsed transfer function method’ HAP analysis for performing cooling load calculations and its validation
The tasks to be done for the completion of the project, initially includes complete site surveying for relevant data collection then drawing an architectural plan for the workshop building employing any suitable software (both ground and first floor). Calculating the cooling load for the building vicinity employing HAP software, and validation of results using manual calculations
| Item Name | Type | No. of Units | Per Unit Cost (in Rs) | Total (in Rs) |
|---|---|---|---|---|
| RAM: 16GB - DDR4 | Equipment | 1 | 4500 | 4500 |
| Hard-drive: AData Ultimate SU800 (256 GB) SSD | Equipment | 1 | 7500 | 7500 |
| 10TH generation Intel Core i7-1005G1 Processor 2.2 GHz | Equipment | 1 | 25000 | 25000 |
| Laptop LCD (15.6”) | Equipment | 0 | 6500 | 0 |
| Motherboard | Equipment | 1 | 10000 | 10000 |
| Seagate 1 TB Mobile HDD | Equipment | 1 | 8000 | 8000 |
| Bluetooth mouse | Equipment | 1 | 800 | 800 |
| Laptop battery | Equipment | 1 | 3500 | 3500 |
| Report Printing (Black And White) | Miscellaneous | 200 | 10 | 2000 |
| Report Binding | Miscellaneous | 1 | 0 | 0 |
| Travelling | Miscellaneous | 4 | 1000 | 4000 |
| Other Accessories | Equipment | 0 | 0 | 0 |
| HAP | Miscellaneous | 1 | 1000 | 1000 |
| Maquac | Miscellaneous | 1 | 1000 | 1000 |
| Report Printing (Color) | Miscellaneous | 50 | 20 | 1000 |
| Total in (Rs) | 68300 |
Tax One time is an application designed to change the way business inside Pakistan handle...
The sudden increase in COVID-19 patients is a major shock to our global health care system...
Umbrellas have practical uses. And we can not only play with its design but like in restau...
A photobioreactor is a bioreactor that utilizes a light source to cultivate phototrophic m...
In this project, we will Design an E-bike and develop a system to collect data using IoT s...