Designing of HVAC system of New Workshop Building of KElectric Korangi Town Gas Turbine Power Station

The purpose of this project is to develop the link between academia and industry. Moreover, students will have a better understanding about the professional working environment. The opportunity is very suitable to enhance the engineering skills of the students.The Workshop Building contains electric

Project Title

Designing of HVAC system of New Workshop Building of KElectric Korangi Town Gas Turbine Power Station

Project Area of Specialization

Mechanical Engineering

Project Summary

The purpose of this project is to develop the link between academia and industry. Moreover, students will have a better understanding about the professional working environment. The opportunity is very suitable to enhance the engineering skills of the students.The Workshop Building contains electrical/instrumental spare parts and machineries for which temperature control is an essential requirement. As we are aware that harsh weather conditions are not favorable for the heat producing machineries and for the spare parts kept in the stores and the tool room. So, in this regard a detailed HVAC design for New Workshop Building shall be developed in compliance with authority regulation & international standards.

Project Objectives

The project involves site surveying to collect relevant data/information for proceeding the project. There are several methods employed globally for cooling load estimations where we would be using ‘Cooling Load temperature difference (CLTD) method’ and ‘ASHRAE-endorsed transfer function method’ HAP analysis for performing cooling load calculations and its validation.The tasks to be done for the completion of the project, initially includes complete site surveying for relevant data collection then drawing an architectural plan for the workshop building employing any suitable software (both ground and first floor). Calculating the cooling load for the building vicinity employing HAP software, and validation of results using manual calculations. Then designing the ducting system for suitable Air conditioning using MCQUAY duct sizer as well as representing the duct in the floor plan. Afterwards, selecting a reasonable chiller unit and AHU according to the load requirements.

Project Implementation Method

The Workshop Building contains electrical/instrumental spare parts and machineries for which temperature control is an essential requirement. As we are aware that harsh weather conditions are not favorable for the heat producing machineries and for the spare parts kept in the stores and the tool room. So, in this regard a detailed HVAC design for New Workshop Building shall be developed in compliance with authority regulation & international standards.

Benefits of the Project

The project involves site surveying to collect relevant data/information for proceeding the project. There are several methods employed globally for cooling load estimations where we would be using ‘Cooling Load temperature difference (CLTD) method’ and ‘ASHRAE-endorsed transfer function method’ HAP analysis for performing cooling load calculations and its validation

Technical Details of Final Deliverable

The tasks to be done for the completion of the project, initially includes complete site surveying for relevant data collection then drawing an architectural plan for the workshop building employing any suitable software (both ground and first floor). Calculating the cooling load for the building vicinity employing HAP software, and validation of results using manual calculations

Final Deliverable of the Project

Software System

Core Industry

Energy

Other Industries

Core Technology

Others

Other Technologies

Clean Tech

Sustainable Development Goals

Industry, Innovation and Infrastructure

Required Resources

Item Name Type No. of Units Per Unit Cost (in Rs) Total (in Rs)
RAM: 16GB - DDR4 Equipment145004500
Hard-drive: AData Ultimate SU800 (256 GB) SSD Equipment175007500
10TH generation Intel Core i7-1005G1 Processor 2.2 GHz Equipment12500025000
Laptop LCD (15.6”) Equipment065000
Motherboard Equipment11000010000
Seagate 1 TB Mobile HDD Equipment180008000
Bluetooth mouse Equipment1800800
Laptop battery Equipment135003500
Report Printing (Black And White) Miscellaneous 200102000
Report Binding Miscellaneous 100
Travelling Miscellaneous 410004000
Other Accessories Equipment000
HAP Miscellaneous 110001000
Maquac Miscellaneous 110001000
Report Printing (Color) Miscellaneous 50201000
Total in (Rs) 68300
If you need this project, please contact me on contact@adikhanofficial.com
Tax One Time

Tax One time is an application designed to change the way business inside Pakistan handle...

1675638330.png
Adil Khan
9 months ago
Covid-19 Detection Using AI

The sudden increase in COVID-19 patients is a major shock to our global health care system...

1675638330.png
Adil Khan
9 months ago
Techno Umbrella

Umbrellas have practical uses. And we can not only play with its design but like in restau...

1675638330.png
Adil Khan
9 months ago
Fabrication and development of Algae bioreactor for biomass production...

A photobioreactor is a bioreactor that utilizes a light source to cultivate phototrophic m...

1675638330.png
Adil Khan
9 months ago
IoT based e-bike with Intelligent Traction Drive System with longer dr...

In this project, we will Design an E-bike and develop a system to collect data using IoT s...

1675638330.png
Adil Khan
9 months ago