The main objective of this project is to propose a ?Solar and Wind Hybrid Energy Dispatch System? as a solution to the existing flaws in the energy management system of Pakistan. Over a decade, Pakistan has suffered from serious energy crisis and struggled to bridge the gap between the demand and su
Design and Implementation of Solar and Wind Hybrid Energy Dispatch System
The main objective of this project is to propose a “Solar and Wind Hybrid Energy Dispatch System” as a solution to the existing flaws in the energy management system of Pakistan. Over a decade, Pakistan has suffered from serious energy crisis and struggled to bridge the gap between the demand and supply of electricity with an ever-growing population has had lasting impacts on the country both economically and environmentally. The world is planning on shifting to eco-friendly means of power generation methods in order to reduce the amount of pollution caused by the burning of fossil fuels to produce electricity whereas Pakistan’s power generation relies a great deal upon fossil fuels which is now economically exhausting the country. Renewable Resources are the most environmentally sound solution to fill the energy supply and demand gap and reduce the economic burden. Solar Energy and Wind Energy are the most prominent renewable resources. Pakistan is blessed because the Solar and Wind potential in the country is high and it can produce sufficient electricity in order to fill the gaps. However, the Solar technology in Pakistan has matured and requires upgradation to inexpensive technology to make more use out these energy generation methods. Hybridization of Solar and Wind is the key to overcome the unreliable and weather dependent nature of both these resources.
Hybrid systems have been found to be more economically practical alternatives to fulfil the energy demands. Merging of solar and wind energy into a hybrid generating system can also enervate their individual fluctuations, increase overall energy output, and reduce energy storage requirement remarkably. At times when neither wind nor solar is producing the desired amount of electricity the hybrid systems provide power through batteries or through an engine generator powered by conventional fuels. The method proposed requires the introduction of a Maximum Power Point Tracking (MPPT) algorithm in the DC-DC Boost converter in order to extract the maximum efficiency individually of both these resources. The design of Multi-Level Inverters to convert DC output of battery to a smooth sinusoidal AC. The working system will be able to hybridize both the sources and generate a smooth sinusoidal output using Harmonics Elimination.
Key objectives of the project are:
Implementation steps of the project are as follows.
Following are the some of the benefits of the project:
Final deliverable of the project is a prototype of “Solar and Wind Hybrid Energy Dispatch System” with capability to power AC loads as well as DC loads. Final model will consist of PV panels and DC wind turbine connected with DC-DC boost converters. Maximum Power Point Tracking MPPT algorithm will be implemented on these converters to extract the maximum power from these energy sources. Output of these converters will be hybridized at DC point using a DC bus. The designed DC bus will also be used as a hybrid controller to control the switching of output voltage from both the sources. Four switching modes of the hybrid controller depending on the availability of solar energy and wind energy are as follow.
Switching will base on the output of DC-DC converters compared to reference DC voltage of DC bus. DC bus will be connected to charge controller also based on DC-DC converter. Charge controller will be able to charge the batteries and power the DC load connected directly to it. Final and foremost part of the project will be an inverter integrated with charge controller for conversion of DC into smooth sinusoidal AC (~220V) to power AC loads.
| Item Name | Type | No. of Units | Per Unit Cost (in Rs) | Total (in Rs) |
|---|---|---|---|---|
| Solar Panel 80W | Equipment | 1 | 5000 | 5000 |
| Lead Acid Battery | Equipment | 4 | 4000 | 16000 |
| Oscilloscope | Equipment | 1 | 4500 | 4500 |
| DC Power Supply | Equipment | 1 | 3000 | 3000 |
| Controller (Arduino Mega) | Equipment | 2 | 2000 | 4000 |
| Voltage Sensor | Equipment | 8 | 100 | 800 |
| Current Sensor | Equipment | 8 | 350 | 2800 |
| LUX Meter | Equipment | 1 | 3300 | 3300 |
| Tachometer | Equipment | 1 | 3500 | 3500 |
| Anemometer | Equipment | 1 | 2800 | 2800 |
| Consumeable Electronic Items | Equipment | 1 | 8000 | 8000 |
| LCD 16x2 | Equipment | 4 | 350 | 1400 |
| I2C Module | Equipment | 4 | 200 | 800 |
| Digital Multimeter | Equipment | 1 | 1500 | 1500 |
| Vero Board | Equipment | 8 | 75 | 600 |
| Soldering Kit | Equipment | 1 | 2000 | 2000 |
| 48V-220V Inverter | Equipment | 1 | 10000 | 10000 |
| Overheads | Miscellaneous | 1 | 4000 | 4000 |
| Printing | Miscellaneous | 1 | 1500 | 1500 |
| Stationary | Miscellaneous | 1 | 1500 | 1500 |
| Prototype Modelling | Miscellaneous | 1 | 3000 | 3000 |
| Total in (Rs) | 80000 |
The exponential growth of the Internet over the past several years has placed a tremendous...
The project is a Passive configurable knee joint which is specifically designed to be in t...
Low-fidelity prototyping is a renowned method of developing concepts for traditional two-d...
It is a key figure in smart grids that the generation of electricity meet the demand of th...
This Project addresses an approach to intelligent safety control of passengers on escalato...