Induction Hardening is an activity which is used for the surface hardening of steel and other alloy components i.e: gears, crankshafts, camshafts, drive shafts, output shafts, torsion bars, rocker arms, CV joints, tulips, valves, rock drills, slewing rings, inner and outer races. We will design VFD
UPGRADATION OF POWER SUPPLY OF INDUCTION HARDENING MACHINE
Induction Hardening is an activity which is used for the surface hardening of steel and other alloy components i.e: gears, crankshafts, camshafts, drive shafts, output shafts, torsion bars, rocker arms, CV joints, tulips, valves, rock drills, slewing rings, inner and outer races. We will design VFD based induction heating prototype.
The objective of this paper is all about the modification of the Power Rectifier Induction Machine. The main interest of this paper is
| Activity | October 2021 | November 2021 | Dec 2021 | Jan-Feb 2022 | Mar-Apr 2022 | May-June 2022 | ||
| Collection of Literature | ? | |||||||
| Study of Literature | ? | |||||||
| Analysis of Proposed Scheme | ? | |||||||
| Preparation of Schemes / Model | ? | |||||||
| Implementation of Schemes/Model | ? | |||||||
| Analysis & Simulation, Hardware Testing | ? | |||||||
| Result Formulation | ? | |||||||
| Final Write-up & FYDP Report Submission | ? | |||||||
Activity
Collection of
Literature
Study of Literature
Analysis of Proposed Scheme
Preparation of
Schemes / Model
Implementation of Schemes/Model
Analysis & Simulation, Hardware Testing
Result Formulation
Final Write-up &
FYDP Report Submission
This project “Design of power supply of A8-21 Induction Hardening Machine” leads to a smooth use of the machine. As this is an industrial project (HIT), so it will help the industry in reliability and control output frequency, voltage or temperature according to their requirements.
This project “Design of power supply of A8-21 Induction Hardening Machine” leads to a smooth use of the machine. As this is an industrial project (HIT), so it will help the industry in reliability and control output frequency, voltage or temperature according to their requirements.
| Elapsed time in (days or weeks or month or quarter) since start of the project | Milestone | Deliverable |
|---|---|---|
| Month 1 | Proposal | Yes |
| Month 2 | Studying literature review | Yes |
| Month 3 | Simulation | Yes |
| Month 4 | Studied how to make the project more reliable | Yes |
| Month 5 | Implementing Hardware | Yes |
| Month 6 | Upgradation in Hardware | In progress |
| Month 7 | Rechecking of Hardware | No |
| Month 8 | Final Delivery | No |
My project is Online Fyp Management System.I with my group members made website using HTML...
We are doing project of fingerprint base electronic attendance using aurdino. Attendance s...
In this project, a simple energy meter can be turned into a di...
Summary of the project: This project is about the design of a hardware system that uses an...
We need robots in places where human is physically unable to reach, such as planet explora...