Power outage is common in our daily life. It not only affect consumers but also power utilities in the long run. About 70% of the faults occur due to short circuit and overloading and it gets worst in summer season as electricity demand incre
SCADA Based Power Distribution Network
Power outage is common in our daily life. It not only affect consumers but also power utilities in the long run. About 70% of the faults occur due to short circuit and overloading and it gets worst in summer season as electricity demand increases. If we can find a way to minimize the duration of such faults, we can contribute in improving life quality of many people. Our final year project (FYP) idea revolves around this problem.
When Over-current fault (i.e., short circuit and overloading) occur the power utilities depend on consumer complaints or the surveying team to pin point the faulty transformer (pole mounted). Our project uses centralized Supervisory Control And Data Acquisition (SCADA) system which takes information of current flowing through PMTs (Pole Mounter Transformers) and determines when a fault has occurred (measured current flow would be zero). Once fault is detected, the operator using the software in his office can take several attempts to reclose the system (using auto-reclosers) as most of the faults are temporary. But in case of permanent fault the system would trip again and he would know the exact transformer tripped. Now he can easily dispatch a team of technicians to remove the fault as soon as possible. In this way time take for fault localization and removal of temporary faults by actually reaching the transformer is saved. Since the system is closed-loop PLC(Programmable Logic Controller) would also be used along with RTUs (Remote Telemetry Units).
Our Goal is to develop a prototype based on the above mentioned points which can also be used as a trainer to make students/trainees more familiar with automated power system.
Following are the main objectives of our Final Year Project that is SCADA Based Power Distribution Network.
Following are the step-by-step process through which we will implement the project.
Time Frame is depicted below.

Following are the key benefits of our project:
The project diagram/flow chart is depicted below:

SCADA SOFTWARE:
We will be using LabVIEW with OPC server as our central SCADA hub which will collect information from RTUs about current values in order to distinguish between normal and fault condition. Later pass information to operate circuit breaker if fault condition occurs.
Three Phase Supply:
We will first step up our house three phase supply to 1100 Volts by a 1.5 kVA 3-phase transformer.
PMTs (Pole Mounted Transformers):
We will connect three separate 3-phase transformers depicting PMTs of a power utility to our main supply. These are the transformers which would be protected in fault conditions each transformer is of 500VA.
Auto-Recloser Circuit Breakers:
These will be the actuators which would open circuit the supply to load in case of fault. Operator can reclose the circuit multiple times to ensure the fault isn’t temporary.
Current Sensors and Load:
Each PMT would be connected with variable 3-phase load which can be set to maximum 500 Watts. Current sensors would measure the amount of current flowing from PMT to load and send the measurements to main system.
Remote Telemetry Units (RTUs):
These are responsible to read data from environment (in our case current flow) and send it to the software which is controlling the process (i.e., SCADA).
Programmable Logic Controllers (PLCs):
PLC here is acting like the hand of the software while RTUs are acting as eyes. PLC will take info from SCADA software and based on it toggle the Auto-Recloser CB. We will be using Delta PLC model: dvp 14ss2 programmed with ladder logic.
| Item Name | Type | No. of Units | Per Unit Cost (in Rs) | Total (in Rs) |
|---|---|---|---|---|
| Step-up Transformer | Equipment | 1 | 13000 | 13000 |
| Step-down Transformers | Equipment | 3 | 4000 | 12000 |
| RTUs | Equipment | 3 | 8000 | 24000 |
| PLC | Equipment | 1 | 12000 | 12000 |
| Current Sensor | Equipment | 3 | 500 | 1500 |
| Load bank | Equipment | 3 | 1000 | 3000 |
| Trainer body | Equipment | 1 | 4000 | 4000 |
| Wires | Miscellaneous | 1 | 3000 | 3000 |
| Printing and pain job | Miscellaneous | 1 | 3000 | 3000 |
| Power consumption during testing (estimated) | Miscellaneous | 1 | 2000 | 2000 |
| Total in (Rs) | 77500 |
Our Project "Visual Assistant For Blind Person via voice Command" is based on Artifi...
The most harmful kind of trash in our oceans today are tiny pieces of plastic that are dif...
Agriculture is the source of living and it also has a countless influence on economy of th...
Energy crisis are on the top in our country. There must be smart solutions for each proble...
We made a system Alumni Management System which is helpful for university Alumni associati...