Power Guard
Energy distribution companies have different partners in Pakistan, like HESCO, LESCO, MESCO, etc, for commercial and domestic usage. The consumers are facing the issue of voltage fluctuation controlling and earth leakage detection in energized lines from the supplier companies randomly. These issues
2025-06-28 16:28:50 - Adil Khan
Power Guard
Project Area of Specialization Electrical/Electronic EngineeringProject SummaryEnergy distribution companies have different partners in Pakistan, like HESCO, LESCO, MESCO, etc, for commercial and domestic usage. The consumers are facing the issue of voltage fluctuation controlling and earth leakage detection in energized lines from the supplier companies randomly. These issues are not rare for the consumers, so the suggest/designed smart electric system based on Arduino-UNO microcontroller integrated with a real-time system, and the developed system is able to automatically control the voltage fluctuations, and current, and indicate the earth leakage.
Project Objectives- The main objective of this project is to protect humans from electric shock and suddenly shunt down the system.
- The objective of this project is to mitigate/control voltage fluctuation issues, that cause appliances failure
- The objective of this project is to detect the earth leakage from the lines and provide protection
- The objective of this project is to generate the reports regarding voltage, current, and power
The circuit can be fundamentally divided into these stages, the first stage to make a circuit to mitigate/control voltage fluctuation issues and make it efficient by doing different experiments to make our appliances protect. The second stage of this project is to make a system that senses and controls if the problem occurs and restart the system. The third stage of this project is to make a protective system for humans because sometimes it gets shocked and the system continues working so it gets a severe injury and sometimes it causes death so this is the first and important objective of this project.
Benefits of the Project- Clear, organized improved plans.
- Defining the role of every component eliminates confusion.
- Well-defined goals for effectiveness.
- Defining an implementation plan.
- Project tools help to increase efficiency.
- Remove the danger from humans.
- Remove the voltage fluctuation issues.
- Increase the system efficiency.
Technical details of final deliverables outline a project's entire scope of work, while deliverables created during earlier phases of a project are probably not selected. Our project's initial deliverables are based on the circuit design of the project and then go for the second deliverables, implementation of the circuit, and the third stage to making a “Thesis” and “Project report”. The ending phase of project deliverables can include a project business because there is a huge market that is waiting for this ‘Power Guard” device.
Final Deliverable of the Project Hardware SystemCore Industry Energy Other Industries Others Core Technology Clean TechOther TechnologiesSustainable Development Goals Industry, Innovation and Infrastructure, Partnerships to achieve the GoalRequired Resources| Item Name | Type | No. of Units | Per Unit Cost (in Rs) | Total (in Rs) |
|---|---|---|---|---|
| Total in (Rs) | 13750 | |||
| Resistors | Equipment | 20 | 5 | 100 |
| Diodes | Equipment | 10 | 20 | 200 |
| Copper Plate | Equipment | 1 | 500 | 500 |
| Choke | Equipment | 2 | 150 | 300 |
| Capacitor | Equipment | 10 | 10 | 100 |
| Capacitive Load | Equipment | 2 | 100 | 200 |
| Blub & holder | Equipment | 2 | 200 | 400 |
| LCD | Equipment | 1 | 300 | 300 |
| Arduino UNO | Equipment | 1 | 2000 | 2000 |
| Connecting Wires | Equipment | 30 | 10 | 300 |
| Transformers | Equipment | 4 | 150 | 600 |
| Changeover Switch | Equipment | 1 | 300 | 300 |
| Connectors | Equipment | 10 | 5 | 50 |
| Switch buttons | Equipment | 4 | 100 | 400 |
| Thesis and Project Report | Miscellaneous | 2 | 4000 | 8000 |