The project is mini hydel generation from overhead water tanks. we are going to utalized potential energy of water storted in the overhead, so whenever any one use water the system will start generation. the pelton turbine is used to rotate the generator. And there is also a display unit which

Project Title

Mini hydel generation from overhead water tanks

Project Area of Specialization

Wearables and Implantable

Project Summary

The project is mini hydel generation from overhead water tanks. we are going to utalized potential energy of water storted in the overhead, so whenever any one use water the system will start generation. the pelton turbine is used to rotate the generator. And there is also a display unit which will monitort different parameters like flow, rpm,current and vibration in the system.

Project Objectives

Following are the Objectives of the project

  • To Utalize hydropower at domestic stage
  • Get clean and green energy without any envoiremental effect
  • Get free energy from usual flow of water
  • Reduce the electricity bill

Project Implementation Method

The project can be implemented in overhead water tanks in societies, colonies and in industries. it can be easilly installed. The pipe coming down from the tank will inlet in the turbine assembly and then exit from turbiune assembly to the user end, so the water will come to the user end rotating turbine

Benefits of the Project

Pakistan facing the serious energy crises. so, this project will generate power to meet the energy demand as much as possible.

Following are the benifits of the project

  • Free of coast energy
  • Every one can use it at homes to generate their own power 
  • It also reduce the cost of electricity used to pump the water in the tanks

Technical Details of Final Deliverable

The main rotating part is turbine so turbine assembly should be fixed properly. the diameter of inlet pipe in the turbine assembly should of 1 inch.The turbine is coupled with generator via gear chains to increase the rpm. 20 volt 18 ampare dc generator is used and a charge controller circuit is designed to provide 12 volt to the battery

Final Deliverable of the Project

Hardware System

Type of Industry

Energy

Technologies

Others

Sustainable Development Goals

Affordable and Clean Energy

Required Resources

Item Name Type No. of Units Per Unit Cost (in Rs) Total (in Rs)
Turbine with Casing Equipment12600026000
Turbine Stand Equipment11100011000
Generator Equipment148004800
Chain gears Equipment113001300
sensor Equipment412004800
Meters Equipment216003200
inverter Equipment135003500
charge controller Equipment120002000
DC and AC loads Equipment213002600
coupler Miscellaneous 27001400
acrylic sheets Miscellaneous 65503300
Depoxy seals and piping Miscellaneous 130003000
colours and finishing Miscellaneous 120002000
fiber box for sen sensors and inverter Equipment312003600
wires and other tools Miscellaneous 1300300
Total in (Rs) 72800
If you need this project, please contact me on contact@adikhanofficial.com
0
159
Monitoring and Controlling of Greenhouse using Internet of Things IoT

The main idea of this FYP to design an autonomous Greenhouse environment. All essential re...

1675638330.png
Adil Khan
1 year ago
Breast Cancer Detection via Microwave Imaging

The goal of this project is to build an integrated microwave imaging system for the early...

1675638330.png
Adil Khan
1 year ago
eSports Manager

Considering the rise and massive boom of the esports industry in Pakistan, our idea addres...

1675638330.png
Adil Khan
1 year ago
Attendance Management System

Attendance is one of those administrative tasks that must be done at the start of each cla...

1675638330.png
Adil Khan
1 year ago
Automatic attendence system through faciel recognition

To maintain the attendance record with day to day activities is a challenging task. The co...

1675638330.png
Adil Khan
1 year ago