Electrical power system is the major source to provide energy for residential, commercial, industrial, and agricultural loads. Now a days, the demand of power is increasing day by day. The difference between demand and supply causes consumers to suffer from the unwanted load shedding. A total blacko
Automatic Priority Based Power Load Switching Using PLC
Electrical power system is the major source to provide energy for residential, commercial, industrial, and agricultural loads. Now a days, the demand of power is increasing day by day. The difference between demand and supply causes consumers to suffer from the unwanted load shedding. A total blackout may occur due to this increase in the power demand. The aim of this project is to automatically disconnect loads when there is not enough energy generation, on priority basis. Using PLC we will automatically turn on or off generators also, according to the requirement of load. Due to disconnection of surplus generators, overall efficiency of power system will be increased.
The implementation of the project consists of following: (1) Power measurement of load and generators using current and potential transformers. (2) Comparison of load power and generation power using PLC programming. (3) Disconnection of low priority loads when demand is more than power generation, using magnetic contactors. (4) Turn off surplus generators if demand is less than power generation. (5) Turn on second generator when demand increases than the maximum rated load of first generator. (6) Automatically synchronize second generator with first one when it is restarted. (7) Real time storage and displaying of power data on HMI.

Figure 1. Objectives for Automatic Priority Based Power Load Switching Using PLC

Figure 2. Implemented Architectural Diagram for Automatic Priority Based Power Load Switching Using PLC

Figure 3. Measuring Instruments Block Diagram on Generators side

Figure 4. Measuring Instruments Block Diagram on Load side
| Item Name | Type | No. of Units | Per Unit Cost (in Rs) | Total (in Rs) |
|---|---|---|---|---|
| PLC FATEK FBS-32MAR2-AC (D24) | Equipment | 1 | 18000 | 18000 |
| FATEK AIO module FBS-6AD | Equipment | 1 | 14550 | 14550 |
| Single phase AC generator (2kW STC alternator) | Equipment | 2 | 13600 | 27200 |
| Motor for driving alternator (FM15 WITH FC 143) | Equipment | 2 | 2200 | 4400 |
| FATEK PLC programming cable | Equipment | 1 | 2300 | 2300 |
| SCT013 Current Transformer (100A / 500mA) | Equipment | 7 | 0 | 0 |
| Potential Transformer (220 / 12V Step down) | Equipment | 7 | 280 | 1960 |
| PUMA digital RPM meter (Tachometer) | Equipment | 2 | 0 | 0 |
| Magnetic contactor 220 V | Equipment | 7 | 0 | 0 |
| Posters, reports and remaining components | Miscellaneous | 5 | 2000 | 10000 |
| Total in (Rs) | 78410 |
Existing video surveillance systems commonly utilize a singular Remotely Pil...
The project Automated Rover and Manipulator System aims to develop a system that can be us...
A growing number of depression cases are going unnoticed or untreated which is giving rise...
A plastic waste recycling machine crushes plastic material, such as plastic bottles, into...
As we can see in todays like that the world is evolving rapidly changing towards medicine...