Traffic Jam is one of the global issues which is faced by many cities throughout the world today. This problem has highest intensity in developing countries. Traffic jams causes disruption of traffic flow which also stop emergency vehicles from approaching to their destinations on time in a matter o

Project Title

Programmable Logic Controller based Traffic Density Control System with Emergency Vehicle Detection

Project Area of Specialization

Electrical/Electronic Engineering

Project Summary

Traffic Jam is one of the global issues which is faced by many cities throughout the world today. This problem has highest intensity in developing countries. Traffic jams causes disruption of traffic flow which also stop emergency vehicles from approaching to their destinations on time in a matter of life and death situations. Huge amount of time is wasted on the roads by the public, fire trucks, police patrols due to traffic jams. In 1912, traffic lights were constructed that were expected to control the smooth passage of vehicles and people at rails and road intersections, pedestrian crossings and other places. This system could not dynamically assign right of way to conflicting movements. Conventional traffic control system does not have any solution for not only density control but also for emergency vehicle detection and management. Since, it is said that conventional practice of traffic control system can be drastically problem creating in sense of density control and detection of emergency vehicle, with the assistance of Programmable Logic Controller (PLC) and sensors this issue can be eliminated for the sake of optimization and automation to control traffic lights in times of emergency. Our proposed system not only resolves the traffic density problem but also the emergency vehicle management This system retains its status before the operation of emergency interrupt which is an essential feature for the management of the traffic.

Project Objectives

  • To construct a Programmable Logic Controller (PLC) based Traffic Control System.
  • To control traffic based on traffic density on the roads.
  • To control traffic based on emergency vehicle detection and management.

Project Implementation Method

Our methodology involves designing a traffic control system at an intersection with four roads. Main concern is to create an infrastructure consisting of special features of density control and emergency vehicle management. There are twelve lights to be operated with the sequence of green, yellow and then red at each road. Normal sequence starts from road one green for 25s and then yellow for 5s. After this road one turns to red, and road two to green and so on. Normal sequence is operated in a loop and it does not stop unless our system is turned off or any interrupts (Density or Emergency) gets operated. There are eight interrupts which are to be operated in accordance with some conditions. The primary focus of our design is to set some conditions for operation of interrupts (Density or Emergency) in a way that some of the dilemmas involved with traffic congestions, are efficiently solved. Emergencies interrupts are taken as high priority because they involve life and death situations where as density interrupts are taken as low priority. Emergency interrupts are operated if and only road 1, road 2, road 3 or road 4 have been given their due time of normal sequence operation where as density interrupts are operated if and only road 4 has been give its due time of normal sequence. These two conditions give priority to emergency interrupts beside controlling density at an intersection. In order to give way to low dense roads, normal sequence runs after every completion of density interrupt. These conditions not only make density of four roads even but also manage emergency vehicle arriving at any of the road. When interrupts are on simultaneously, they can be given priorities based on data concerning emergency and density is analyzed which give information about which road gets dense or emergency arrives at which road more often. 

Benefits of the Project

  • Our project solves the problem of Traffic Jam at any intersection it is implemented at.
  • By operating interrupt based on the emergency vehicle, our project distributes the traffic equally on the roads involved in an intersection.
  • Emergency vehicles are given the highest priority because they contain life and death situations.
  • Our project gives the right of way to emergency vehicles which allows the emergency to approach to its destination faster than the usual.
  • Our project retains the status of normal sequence, before operating any of interrupts, which not only avoids mess on intersection but also allows the rapid flow of traffic.

Technical Details of Final Deliverable

  • Our project will contain Programmable Logic Controller, that will be main component of our deliverable. It will take decisions based on density and emergency.
  • Density inputs will be taken through ultrasonic sensors.
  • Emergency vehicle detection will be done through Radio Frequency modules that will be integrated to arduinos which will be connected to Programmable Logic Controller.
  • There will be twleve signals to be connected to Programmable Logic Controller as inputs.
  • Programmable Logic Controller will be supplied 24v DC from Power supply.
  • Programmable Logic Controller will be able to be controlled through Human Machine Interface, since they will be integrated. 

Final Deliverable of the Project

HW/SW integrated system

Core Industry

IT

Other Industries

Others

Core Technology

Others

Other Technologies

Sustainable Development Goals

Industry, Innovation and Infrastructure, Sustainable Cities and Communities

Required Resources

Item Name Type No. of Units Per Unit Cost (in Rs) Total (in Rs)
Programmable Logic Controller Equipment11600016000
Power Supply 24v DC Equipment135003500
Signals Equipment143004200
Arduino Uno Equipment513006500
Radio Frequency Sensor Equipment413005200
Ultrasonic Sensors Equipment43001200
Wires and cables Equipment10010010000
9 pin d type connector Equipment110001000
232 Usb converter Equipment110001000
Human Machine Interface (HMI) Screen Equipment11000010000
Stationary Miscellaneous 130003000
Printing Miscellaneous 105005000
Over head Miscellaneous 120002000
Total in (Rs) 68600
If you need this project, please contact me on contact@adikhanofficial.com
0
188
Employee management system of national rular support programme

The National Rural Support Programme (NRSP) is a national entity whose mandate is to...

1675638330.png
Adil Khan
1 year ago
Word Web

Learning through playing games and positive reinforcement seems to work better for cogniti...

1675638330.png
Adil Khan
1 year ago
Hardware Realization of bidirectional DC-DC Converter

Bidirectional dc to dc converter is used as a key device for interfacing the storage devic...

1675638330.png
Adil Khan
1 year ago
Mindquil

Anxiety is a common problem faced by not just the Pakistani population but by many people...

1675638330.png
Adil Khan
1 year ago
Smart Irrigation, Crop Enhancement and Agricultural Waste Management u...

The agriculture sector is the prime consumer of water resources that consumes about 70% of...

1675638330.png
Adil Khan
1 year ago