The project Automated Rover and Manipulator System aims to develop a system that can be used to aid workers/technicians, in the manufacturing industry carry heavy loads between different assembly and storage areas. The team has approached a company where the current system involves technic
Automated Rover and Manipulator System (ARMS)
The project Automated Rover and Manipulator System aims to develop a system that can be used to aid workers/technicians, in the manufacturing industry carry heavy loads between different assembly and storage areas. The team has approached a company where the current system involves technicians having to lift heavy switch gear equipment from ground level and then haul the equipment from the storage area to the assembly area. The process also involves the equipment being stored in buffer storage areas in bulk, and then manually retrieved from the buffer storage area and hauled to the assembly area as and when required.
The current labour intensive process decreases productivity while leading to numerous health and safety issues. To mitigate these issues and improve the process, the team has decided to approach the problem with a two-tier solution. the first tier involves a manipulator system that will lift the heavy equipment from the ground level. The second tier involves a system that will be used to transport the equipment from the storage bay directly to the assembly area. The retrieval of the equipment will be completely autonomous and this will be achieved by integrating a communication system between the two separate tiers. The technician will have a user input terminal using which, he will be able order the required amount of equipment needed.
For the first tier of the solution, the team is opting for a SCARA class configuration robot to do the lifting while the second tier will use an automated guided rover to shuttle the equipment between the storage area and the assembly area.
The project aims to tackle a number of general issues that can be found common place in manufacturing facilities while also creating a tailor-made solution for the company.
The current factory floor layout does not allow for expansive solutions hence the Robot will be designed to be as compact as possible keeping in view the limitations of the factory layout. The solution will also require an integrated safety and obstacle avoidance system as both the robot and the rover will have to operate alongside the presence of human workers hence safety is key. The current walkways and paths are compact and do not have the capacity to handle high volumes of traffic hence the shuttle system will have to be designed in a way to transport the equipment in an efficient manner. The system will also incorporate a database management system that will be used to log the orders made my technicians.
The project also aims to increase the productivity of the technicians and simplify the current process by removing the need for buffer storages.
The team has charted an extensive course of action to ensure timely completion of the project. the scope of work was identified into 4 main areas for which each team member is given the responsibility of.
The flow of work for successful completion of the project has been divided into steps with some steps being carried out in parallel.
After the successful completion of the steps above the project will finally be successfully deployed.
The project aims to solve a number of problems associated with the current process. firstly, the biggest problem that the current process induces is the strain on the technician's back incurred by repetitively picking heavy loads from ground level and then carrying it between storage bays and the assembly areas. This also induces fatigue and decreases the productivity of the technicians and also takes time out of their schedules that can be utilised for tasks that require more human input. The automated rover and manipulator system will solve all of the problems stated above by automating this process which will improve the workplace ergonomics while also increasing the quality of life of the technicians. the mundane and repetitive fetching of the equipment’s will be handled by the system and this will boost productivity of the technicians and even increase the output of each technician.
The system not only proves beneficial to the technicians, it also removes the need for the buffer storage area which frees up real estate on the factory floor allowing the company to utilise the space in a better and efficient manner. The system proposed will improve the logging and tracking of equipment’s being signed out by the technicians as the system will maintain a database of each order which can be referenced to later on if the need arises. Carrying heavy loads over long distances can also make the technicians more prone to accidents and drop hazards and these issues are further intensified when the equipment being carried is heavy. letting the rover shuttle the heavy equipment mitigates the risk associated with drop hazards and also makes the overall system more efficient and faster whilst also removing chances of human error.
The team aims to deliver a full working scaled down prototype of the concept proposed which includes:
Hardware:
Software:
The above-mentioned points include all the aspects of the proposed concept that are required to deliver a proof of concept.
| Item Name | Type | No. of Units | Per Unit Cost (in Rs) | Total (in Rs) |
|---|---|---|---|---|
| Stepper motors with gearboxes | Equipment | 4 | 4500 | 18000 |
| leadscrew set | Equipment | 2 | 2000 | 4000 |
| Controller | Equipment | 2 | 4000 | 8000 |
| Raspberry pi | Equipment | 2 | 8000 | 16000 |
| camera | Equipment | 1 | 4000 | 4000 |
| Direct DC drive motors | Equipment | 2 | 2000 | 4000 |
| Electronic speed controller | Equipment | 2 | 3000 | 6000 |
| Battery | Equipment | 1 | 5000 | 5000 |
| Radio transceivers | Equipment | 4 | 1000 | 4000 |
| Total in (Rs) | 69000 |
Our final year project will utilize the concepts of image enhancement, cascade detection,...
The project is Water trash Collector that works on water surface for collecting float...
The scope of this project is to develop a web application for beginners to enhance their k...
The idea is to design a back massager that will provide massage therapy. The structure of...